Accurates was invited to investigate the
work patterns of a flagship power
station, operated by a major global
industrial conglomerate, with a view to
obtaining discretionary rate relief.
We tracked the generator plant's
performance data and our experts also
worked with the plant manager to
establish the areas where operational
efficiency would have been affected by
the maintenance programme.
Arguing the case for discretion
Our team then submitted a well argued
report to the local billing authority
setting out the key events, and showing
how the effect of this work satisfied the
authority's criteria for exercising
discretion in its rate charges.
We also had to make sure that our
proposal complied with the position
taken by the regional government on
discretionary relief and empty rating,
following changes in the law introduced
from 1 April 2008.
Accurates' submission won the argument
and, as a result, we saved the client
£400,000 in discretionary business rate
allowances within a single year.
|